Project /
Task |
Proj.
Completed |
# Days |
Complete |
|
1 |
Place Hardware Inventory Online |
7/2/2008 |
1 |
In Progress |
|
2 |
Wire New HS Computer Lab |
7/3/2008 |
1 |
DONE |
|
3 |
Install remaining overhead projectors |
7/7/2008 |
1 |
DONE |
|
4 |
Create Master
Images |
7/08/08-7/10/09 |
2 |
In Progress |
|
5 |
Create Building
Images |
7/11/2008-7-12/2008 |
2 |
In Progress |
|
6 |
Create
Customized Images |
7/14/08-7/16/08 |
2 |
In Progress |
|
7 |
Reimage All High
School Computers |
7/17/08-7/23/08 |
6 |
|
|
8 |
Reimage All
Middle School Computers |
7/17/08-7/23/08 |
6 |
|
|
9 |
Reimage All
Elementary School Computers |
7/24/08-7/25/08 |
2 |
|
|
10 |
Wire New ES Computer Lab & Install
Smartboard and Overhead Projector |
7/31/08 |
1 |
|
|
11 |
Install Smartboard in
MS Room 203 w/ 1/2 size wipeboards |
08/01/08 |
1 |
|
|
12 |
Run new
networking cables for the HS Caf |
08/04/08 |
1 |
|
|
13 |
Install pull
down Screen in MS Conference Rm |
08/05/08 |
1 |
|
|
14 |
Install pull
down screen in ES Conference Rm |
08/05/08 |
1 |
|
|
15 |
Install Overhead
projector and SS in MS Library |
08/05/08-08/06/08 |
2 |
|
|
16 |
Order and
install overhead projectors for
Pesterino, Brazeau |
08/07/08 |
1 |
|
|
17 |
Order and
install overhead projector &
Smartboard for HS Computer Lab |
08/07/08 |
1 |
|
|
18 |
Setup All
classrooms with computers, etc... |
08/08/08-08/15/08 |
7 |
|
|
19 |
Get Joe setup
with new computer & monitor |
08/18/08 |
1 |
|
|
20 |
Setup all Power
School Users |
08/19/08-08/21/08 |
3 |
|
|
Other IT
Projects for Tech Director |
|
1 |
Install Power
School Server |
07/07/08 |
|
|
|
2 |
Install new T-1
Line at High School |
07/07/08 |
|
|
|
3 |
Install new T-1
Line at Middle School |
07/07/08 |
|
|
|
4 |
Get MS & SAU
wired with Internal Cell Antennas |
08/25/08 |
|
|
|
5 |
Get new
Fiberopic connection up and running |
08/01/08 |
|
|
|
6 |
Renetwork VPN so
all sites are viewable |
08/03/08 |
|
|
|
7 |
Remove Raymond
SAU Domain and switchover users |
08/03/08-08/04/08 |
|
|
|
8 |
Install
Nutrisystem on MS Server |
08/05/08 |
|
|
|
9 |
Connect
Nutrikids remote station to MS Server
|
08/05/08 |
|
|
|
10 |
Complete Reader
Pilot program details |
08/06/08 |
|
|
|
11 |
Establish Remote
backup from All Schools |
08/27/08 |
|
|
|
12 |
Upgrade
Look/Feel of District Website |
Ongoing |
|
|