IT PROJECT # 10

 

  Assess and Install Battery Backup Protection for Critical Network Hardware


     One of the first tasks the new IT department did was to do a complete on sight hardware evaluation.  During this process we discovered the types of networking infrastructure and began to understand how it all "fit together".  During these assessments we noted a number of insufficient battery backup units to protect essential network architecture. 

PHASE 1: Provide new Battery backup units for all Mission Critical hardware.

STATUS: As of 3/11/08

Raymond High School:  All servers routers, switches have at least minimal battery backup protection.  All WinSchool Stations are now equipped with Backup 500 floor units.

IHGMS:  All servers, routers and switches have at least minimal battery backup protection.

LRES:  Requirements are noted, insufficient funding currently available to properly protect all servers.

SAU Building:  Requirements are noted, insufficient funding currently available to properly protect all servers.  Many stations at the SAU have at least minimal battery backup units.
 

FUTURE PLANS:  There are several new network designs being discussed that would consolidate existing network servers, thus requiring fewer APC backups.  As of 3/11/08 we are still in the theorizing stage but several consolidation plans have emerged which could save the district thousands of dollars in new hardware.  Updates on this will be posted as we continue this process.

    